LESSON 3 OF 4 · 12 MIN
PM tools: RFI, submittal, change
Move a question and a change through the formal tools instead of text messages.
RFI
A request for information is a formal question when the drawings or specs are unclear, conflicting, or silent. A good RFI cites the sheet and detail, asks one question, proposes a solution if you have a responsible one, and states whether you think there is cost or time impact. A bad RFI is a novel, or a question the spec already answered on page two.
Distribution matters. The official response is the one in the tool, not the text the architect sent the super at 9 p.m. If you act on the text and the formal answer differs, you own the rework.
Submittals
Submittals prove the product you intend to install matches the spec: data sheets, shop drawings, samples. They are organized by spec section, they have a workflow (contractor, then reviewer), and they are not approved just because the box arrived. 'Approved as noted' means read the notes before you order.
Change events and meetings
A change event is the bucket for a potential cost or schedule change before it becomes a change order. RFIs with impact, unforeseen conditions, and owner asks land there so money is visible early. Meetings have agendas, minutes, and action items with owners. If it is not in the minutes, it did not happen — that is the culture you should expect at firms that already run on Procore.
CHECK YOURSELF
The drawings conflict on a flashing detail. Best first move?
Fieldbook is original study material so you walk into each paid course already oriented. It is not the ASTM standard, an OSHA outreach card, an ICC exam, a TREC license, or BCSP’s item bank. Code numbers and blueprint weights change by edition. Confirm them in the book or bulletin you will be tested on. Nothing here is legal, licensing, or benefits advice for your VR&E file.